The status of implementation and execution of PCPIR projects is as follows:
Indicator | Gujarat | Andhra Pradesh | Odisha |
---|---|---|---|
Location/ Region | Dahej, Bharuch | Vishakhapatnam– Kakinada | Paradeep |
Date of Approval | Feb, 2009 | Feb, 2009 | Dec, 2010 |
Date of MoA | 07.01.2010 | 01.10.2009 | 03.11.2011 |
Total Area (Sq. kms.) | 453.00 | 640.00 | 284.15 |
Processing Area (Sq.kms.) | 230.00 | 270.00 | 123.00 |
Anchor Tenant | ONGC Petro Additions Limited (OPaL) | Yet to be finalized | Indian Oil Corporation Ltd. (IOCL) |
Refinery / Cracker capacity in MMTPA | Cracker: Ethylene: 1.1 Propylene: 0.6 | Yet to be finalized | 15 (Greenfield refinery). |
Anchor Project Status | Commissioned in March, 2017 | Yet to be finalized. | Commissioned in February, 2016. |
Amount of approved infra. projects (Rs. crore)* | NA | 18,731.00 | 13,634.00 |
GoI share in form of VGF (Rs. crore) | 80.50 | 1206.80 | 716.00 |
Total proposed investments (Rs. crore)* | 50,000 | 3,43,000.00 | 2,77,734.00 |
Investments made (Rs. Crore) | 1,24,137 | 18,148.00 | 47,000.00 |
Projected employment (No.)* | 8,00,000 | 11,98,000 | 6,48,000 |
Employment generated (No.) | 2,38,000 | 1,41,204 | 40,000 |
Status of Master Plan notification | Development Plan sanctioned. | Field Studies, village level consultations completed. Once the Anchor unit finalizes location, configuration and capacity of the Cracker Complex etc., Master Plan will be finalized. | Preparation of Master Plan is in process. |
Status of EIA | Environmental Clearances & Coastal Region Zone received. | Environmental Clearances, EIA Studies, Collection of Baseline Data etc completed. Once the Master Plan finalized based on location, configuration and capacity of the Cracker Complex the public hearing will be conducted and will be processed for Environmental Clearance. | The draft EIA & EMP Report has been prepared based on the fresh ToR issued by MoEF&CC and same has been submitted to Odisha SPCB for the conduct of hearing in Jagatsinghpur & Kendrapara District. |