PCPIR

Policy Resolution for Promotion of Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs)

The status of implementation and execution of PCPIR projects is as follows:

IndicatorGujaratAndhra PradeshOdisha
Location/ RegionDahej, BharuchVishakhapatnam– KakinadaParadeep
Date of ApprovalFeb, 2009Feb, 2009Dec, 2010
Date of MoA07.01.201001.10.200903.11.2011
Total Area (Sq. kms.)

453.00

640.00284.15
Processing Area (Sq.kms.)

230.00

270.00

123.00
Anchor Tenant

ONGC Petro Additions Limited (OPaL)

Yet to be finalized

Indian Oil Corporation Ltd. (IOCL)

Refinery / Cracker capacity in MMTPA

Cracker:

Ethylene: 1.1

Propylene: 0.6

Yet to be finalized

15 (Greenfield refinery).

Anchor Project Status

Commissioned in March, 2017

Yet to be finalized.

Commissioned in February, 2016.

Amount of approved infra. projects (Rs. crore)*NA18,731.0013,634.00
GoI share in form of VGF (Rs. crore)80.501206.80716.00
Total proposed investments (Rs. crore)*50,0003,43,000.002,77,734.00
Investments made (Rs. Crore)1,24,13718,148.0047,000.00
Projected employment (No.)*8,00,00011,98,0006,48,000
Employment generated (No.)2,38,0001,41,20440,000
Status of Master Plan notification

Development Plan sanctioned.

Field Studies, village level consultations completed. Once the Anchor unit finalizes location, configuration and capacity of the Cracker Complex etc., Master Plan will be finalized.

Preparation of Master Plan is in process.

Status of EIAEnvironmental Clearances & Coastal Region Zone received.Environmental Clearances, EIA Studies, Collection of Baseline Data etc completed. Once the Master Plan finalized based on location, configuration and capacity of the Cracker Complex the public hearing will be conducted and will be processed for Environmental Clearance.The draft EIA & EMP Report has been prepared based on the fresh ToR issued by MoEF&CC and same has been submitted to Odisha SPCB for the conduct of hearing in Jagatsinghpur & Kendrapara District.